Skip to content
Technology How it works Breeder — Hyperion Burner — Aegis Burner — MetroVolt AI-Native Architecture Magnets Fuel cycle Safety Roadmap
Solutions AI & Data Centers Defense & Government Grid & Baseload Neutron Detection Quantum
Learn Technical Library
Proof Publications Whitepapers Technical Library Open Science & Reproducibility The Honest Gates
Company About / Mission Leadership Environment Health & Safety Investors Careers Press Contact
3D Model
Aegis › Fuel & Supply
Fuel & Supply

Helium-3 Inventory Management

Because helium-3 arrives slowly by decay, the supply is managed as an inventory — a reserve built ahead of demand rather than produced on demand.

A reserve, not a tap

Helium-3 cannot be produced faster by turning a dial: it appears at the fixed rate set by tritium's 12.32-year half-life. That makes helium-3 supply an inventory-management problem. The breeder builds a tritium store, a chosen fraction is allowed to decay, and the resulting helium-3 is accumulated as a reserve. Burners draw down that reserve. The system is planned around stock and flow, not instantaneous production.

STOCK BUILDS AHEAD OF DEMANDtime → (breeder running)3He reservefirst burner draw

The levers

Three levers set the helium-3 reserve. First, how many breeders run and at what tritium breeding ratio (the lever spans 1.1, 1.5, and 1.8). Second, what fraction of bred tritium is held for decay versus sold or used directly as tritium. Third, the timing — because decay is passive, starting the breeder early (construction from Q2 2027) means a reserve exists before the first test burner around 2032.

Managed this way, the slowness of decay becomes a strength: the supply is predictable years in advance and cannot be disrupted by a single event, because most of the future helium-3 already exists as tritium in store.

Content reviewed August 2026 · design-and-simulation stage