MetroVolt › Readiness & Timeline
Readiness & Timeline

What Could Move the Dates

The 2032 and 2036 targets depend on breeder progress, physics results, high-field magnets, and helium-3 — any of which can move them.

Honest about the schedule

The MetroVolt timeline is a plan, and plans for first-of-their-kind machines move. Rather than defend fixed dates, it is more useful to name what would move them — so a reader can judge the schedule against real dependencies.

Breeder scheduleDelays propagate: burner inherits breeder maturity.OPENConfinement resultA plug/stability shortfall forces redesign.OPENHigh-field magnetPlug-magnet development slower than planned.PARTIALHelium-3 supplyFleet fuel path slower to materialize.OPENDEC at scaleConversion efficiency below design.DESIGN

Direction of the risk

Most of these push dates later, not earlier. The breeder schedule is the largest single lever, because the burner’s readiness is built on breeder results. A confinement shortfall is the largest physics lever, because it can force a redesign rather than a delay. Helium-3 constrains the fleet more than the test unit.

Content reviewed August 2026 · design-and-simulation stage