Grid & Cities

The Black-Start Sequence

Restoring a grid proceeds in careful blocks; a near-load firm unit can serve as the anchor that energizes each step.

Bringing a grid back in blocks

Grid restoration is deliberate. A black-start unit first energizes a small, controlled section, called a cranking path, then picks up load in blocks, keeping generation and load balanced and voltage within limits at every step. Adding too much load at once trips the fragile restarting island. Larger plants are started along the path using power the black-start unit provides.

A near-load burner (MetroVolt) with grid-forming control can serve as the anchor for such a sequence in its local area, providing the reference voltage and frequency and the ramping capacity to pick up successive blocks of load.

Restoration stepsSelf-start the unit from on-site or battery powerEstablish a stable voltage and frequency referenceEnergize the cranking path to nearby substationsPick up load in controlled blocks, balancing at each stepSynchronize additional generation onto the islandThe burner acts as the local anchor for these steps.

Why grid-forming matters here

Only a grid-forming source can set the reference that a restoring island needs. Grid-following inverters cannot start a dead grid because they require an existing reference. This is why the burner's inverter design intent includes grid-forming control.

Honest framing

The sequence above is standard grid-restoration practice; MetroVolt's ability to anchor it is a design objective contingent on reliable cold-start, which the plug-regime gate leaves open until the test program.

Content reviewed August 2026 · design-and-simulation stage