Hyperion › Building It First
Building It First

REBCO Magnet Supply

High-field operation at 16.84 T depends on REBCO high-temperature superconductor, the single most constrained item in the build.

Why REBCO

Reaching 16.84 T peak field in a compact spherical tokamak requires high-temperature superconductor. REBCO (rare-earth barium copper oxide) tape carries the current density needed at high field and elevated temperature margin, which is why it anchors the magnet design and the schedule.

The supply constraint

REBCO tape is manufactured by a limited set of producers, and the quantity and quality needed for a full toroidal-field magnet set are substantial. Conductor procurement is therefore a long-lead commitment placed at the start of construction, and conductor qualification, verifying current-carrying performance and defect rates, is part of accepting the supply.

From tape to magnet

Where it is proven

The magnet is proven at gate G2: the coil set must reach and hold 16.84 T peak with 8 T on axis under operational load. REBCO supply quality feeds directly into whether G2 passes, which is why conductor qualification is treated as rigorously as the field test itself.

The magnet is a design informed by REBCO practice; the specific coil set is not yet built. Author reconciliation on some REBCO material details is tracked as an open item in the program's documentation.

Content reviewed August 2026 · design-and-simulation stage