Skip to content
Technology How it works Breeder — Hyperion Burner — Aegis Burner — MetroVolt AI-Native Architecture Magnets Fuel cycle Safety Roadmap
Solutions AI & Data Centers Defense & Government Grid & Baseload Neutron Detection Quantum
Learn Technical Library
Proof Publications Whitepapers Technical Library Open Science & Reproducibility The Honest Gates
Company About / Mission Leadership Environment Health & Safety Investors Careers Press Contact
3D Model
Hyperion › Building It First
Building It First

Construction Begins Q2 2027

Ground and long-lead procurement for the first-of-a-kind breeder are scheduled to begin in the second quarter of 2027.

The start of the build

The program schedule places the start of first-of-a-kind (FOAK) construction in Q2 2027. This is the transition from a design and simulation study to a physical build: site preparation, long-lead procurement of the superconducting magnet materials, and the start of vessel and structural fabrication.

What has to be true to start

Long-lead items drive the date

The pacing items are the high-field magnets and the vacuum vessel. REBCO conductor procurement, coil winding, and structural fabrication have lead times measured in many months, so procurement begins at or near the start of construction even though installation comes later in the sequence. The Q2 2027 date is set by when those long-lead commitments can be responsibly placed.

Construction beginning is not the same as operation. The build is planned as roughly a 3.5-year path to the first unit, with first tritium targeted near 2030. Until the machine is assembled, commissioned, and taken through its physics gates, all performance figures remain design and simulation values.

Content reviewed August 2026 · design-and-simulation stage