Hyperion › Building It First
Building It First
Hyperion breeder · design render
Hyperion breeder · design render · © 2026 KFE

Construction Begins Q2 2027

REBCO critical surface — the magnet operating envelope.
REBCO critical surface — the magnet operating envelope. canon 2026-08-27 · © 2026 KFE

Ground and long-lead procurement for the first-of-a-kind breeder are scheduled to begin in the second quarter of 2027.

The start of the build

The program schedule places the start of first-of-a-kind (FOAK) construction in Q2 2027. This is the transition from an engineering program to a physical build: site preparation, long-lead procurement of the superconducting magnet materials, and the start of vessel and structural fabrication.

What has to be true to start

Long-lead items drive the date

The pacing items are the high-field magnets and the vacuum vessel. REBCO conductor procurement, coil winding, and structural fabrication have lead times measured in many months, so procurement begins at or near the start of construction even though installation comes later in the sequence. The Q2 2027 date is set by when those long-lead commitments can be responsibly placed.

Construction beginning is not the same as operation. The build is planned as roughly a 3.5-year path to the first unit, with first tritium targeted near 2030. Until the machine is assembled, commissioned, and taken through its physics gates, all performance figures remain design and validation values.