Technical Library › Operations & Commissioning
Operations & Commissioning
Performance Demonstration
Sustained operation at the design point, measured against the frozen targets.
- Goal
- Meet frozen targets, measured
The final commissioning stage sustains operation at the design point and measures it against the frozen targets — the breeder's Q = 3.424 and 88.7 MW, the burner's QE = 1.31 under its stated gate conditions. It is where computed design targets meet measured reality.
Kronos frames these targets as the demonstration goal, not a present claim.